Certification Manual
- 14 -
Following this, the Project Manager will produce a wiring diagram,
verify that the correct parts have been ordered and develop a work
sequence for the facility based on the accepted proposal. The Project
Manager will be responsible for the ordering, packing and shipping of all
materials and components needed, making sure that they get to the
installer on site. Check the boxes before beginning the installation to
ensure that all of the items on the order packing list have arrived safely and
without damage.
A Technicians Manual with drawings for each kind of system will be
provided to ensure a smooth installation and conformity to Alliance’s
standards. The Work Sequence and Wiring Diagram documents are
important and to be followed. If there seems to be a reason to change the
sequence or installation concerning them, contact the Alliance Project
Manager first. If the facility administration wants anything extra, this will
have to go through the proper channels before working can begin on those
items.
The Project Manager will have facility layout drawings, wiring
diagrams, work sequences, special instructions and perhaps even photos
for special circumstances. Be sure to study these documents. Walk
through the facility with maintenance personnel and look at the rooms
where components will be installed. Note the location of firewalls and attic
accesses. Find out if there are any special considerations. Get the
schedule of the resident’s meals etc in order to work around these times.
Take note of where the best parking place is for loading/unloading
tools and components. Be sure to ask the facility as well, as there may be
dedicated parking spaces for service vehicles or special considerations.
These may be temporary or permanent so work within the facilities
Comentarios a estos manuales